Ghalemdi Hydropower Project in final stage

MYAGDI, Nov. 28: The construction works of Ghalemdikhola Hydropower Project have progressed around 90 percent of the total physical infrastructure. The project of 5.5-megawatt capacity is likely to come into operation within four months, the officials said.
By Republica

MYAGDI, Nov. 28: The construction works of Ghalemdikhola Hydropower Project have progressed around 90 percent of the total physical infrastructure. The project of 5.5-megawatt capacity is likely to come into operation within four months, the officials said. 


Secretary of Ghalemdi Hydro Limited Bimal Rijal said that development of intake, tunnel, penstock, pipe installation and powerhouse has reached in the final stage adding that test transmission would be done most probably by April 2019. 


Related story

Tunnel construction for Phukot-Karnali semi-reservoir hydropowe...


The project was initiated some four years ago from the industrialists and business leaders of Myagdi district but the project was delayed due to Gorkha Earthquake, India’s economic blockade on Nepal, geographical remoteness and Baisari landslides in the Kaligandaki River. 


The total cost of the project is estimated at around Rs 1.15 billion. 

Likewise, the company is preparing to issue an initial public offering (IPO) of 1.55 million units of share. 


RSS

Related Stories
ECONOMY

Delay of Dana sub-station delays hydropower projec...

ECONOMY

Seti hydropower project in final stage

ECONOMY

NEA signs PPA with Sangrila Hydropower Pvt Ltd for...

ECONOMY

12 years on, Darkhe Khola hydro project still inco...

OPINION

How sustainable is hydropower development in Nepal...