header banner
ECONOMY

NEA plans six cross-border interconnection corridors

KATHMANDU, March 16: Nepal Electricity Authority (NEA) has identified six cross-border interconnection corridors and 11 transmission lines with 22,000 MW generation capacity added within 2035.
By Republica

KATHMANDU, March 16: Nepal Electricity Authority (NEA) has identified six cross-border interconnection corridors and 11 transmission lines with 22,000 MW generation capacity added within 2035.


Speaking at an interaction on Transmission Network System of Nepal organized by Energy Development Council (EDC) in Kathmandu on Wednesday, Kul Man Ghising, managing director of NEA, said that the power utility has identified and planned six cross-border


Related story

‘Interconnection Affection’ on display


Interconnection corridors and 11 transmission lines with a proposed 22,000 MW generation within 2035, as part of its strategy to optimize the energy grid. “NEA will also study the requirements and feasibility of major transmission projects such as East-West transmission highway of 400 kV and 765 kV, Mid-hill transmission corridors of 400 and 220 kV, and North-South corridors of 220 and 400 kV,” he said, highlighting the current structure of transmission network in Nepal.


The discussion that featured talks from various stakeholders in the energy sector of Nepal saw officials from NEA and Independent Power Producers (IPPs) brainstorm on an outline on the current power scenario of Nepal.


On the occasion, IPPs also lamented discrimination by NEA while evacuating power. They said that compensation rate is different for different hydropower projects -- from 45 percent to 90 percent. “Therefore, NEA has to be transparent and equal to power producer companies,” they said, adding that there was a special provision for transmission line for foreign producers but not to domestic producers.


The IPPs also stressed the need for a stable policy and more coherent approach from NEA. Giving an example where the construction of double-circuit instead of single-circuit could have evacuated more energy, they further said that IPP are ready to adopt Build-Own-Operate-Transfer (BOOT) model or even take the responsibility in land acquisition and procurement if allows. “IPPs are ready to adopt any favorable modality and are open to help the NEA to build transmission line,” they said.

Related Stories
ECONOMY

NEA to make supply of electricity reliable in Mora...

SOCIETY

MTPD to open traffic along river corridors in capi...

ECONOMY

Nepal, China to study expediting development of 3...

WORLD

Russia says it will open humanitarian corridors to...

SOCIETY

As private hospitals turn away COVID patients, gov...