header
                        banner
ECONOMY

Construction of Dana-Kusma transmission line in final phase

KATHMANDU, May 23: The construction of a transmission line from Dana of Myagdi to Kusma of Parbat under the Kaligand...
By Republica

KATHMANDU, May 23: The construction of a transmission line from Dana of Myagdi to Kusma of Parbat under the Kaligandaki Corridor 220 kV transmission line is in the final phase.


According to the officials of the project, the construction is taking place with the aim of bringing the transmission line into operation by July. The work under the project is being carried out even during the lockdown with security management in coordination with the local government and administration. Construction of a 220/132 kV substation at Khurkot is ongoing and equipment has been installed at the substation.


NEA’s Managing Director Kulman Ghising said that the work is taking place with the aim of bringing the Dana-Kusma section into operation by this July. The electricity generated from the 42 MW Mistri River Hydropower Project, that is being built with investments from the private sector  and the 11.2 MW Thapa Khola Hydropower Project will be connected to the transmission line. The electricity will be connected to the national grid through the Dana substation. Currently, Thapa Khola’s electricity is being transmitted through a 33kV line.


Related story

Dana-Khurkot transmission line and substation ready


“The project was supposed to come into operation by April but its construction was affected due to the lockdown,” Ghising said, “The team is working in coordination with chief district officers and head of the local government in order to start its operation by July.”


Of the 110 towers under the 39-kilometer Dana-Kusma transmission line, installation of only one tower is left. The installation has been halted after the locals of Annapurna Rural Municipality of Myagdi obstructed the project at Pokharibagar. Now the installation of the tower has started after discussion with the locals.


NEA project management directorate chief, Manoj Silwal informed Republica Online that the installation of tower is going on and after placing wires on them, the rest of the work will be completed and the line will be charged within July.


Project Head Chandan Kumar Ghosh said, “Placement of only 3 kilometers of wire is left in Myagdi and Parbat and the lack of manpower due to the lockdown has hampered the construction work.”


The construction of the Kaligandaki Corridor transmission line was started with investments from Nepal government, NEA and concessional loan from the Asian Development Bank to evacuate the electricity generated from hydropower projects that will be built in the Kaligandaki river basin.

Related Stories
ECONOMY

Phase II of Kabeli Corridor Transmission Line read...

1 min read
SOCIETY

Test transmission of Khimti-Dhalkebar transmission...

1 min read
ECONOMY

Seven towers ready for construction of transmissio...

1 min read
ECONOMY

Construction of three int’l power transmission lin...

1 min read
ECONOMY

First phase construction of Koshi Corridor 220 KV...

1 min read