With 3 days remaining of PM's deadline, govt agencies expedite road repair

KATHMANDU, July 27: The government has claimed that fixing potholes and repairing roads inside the Kathmandu Valley has been expedited following the direction from the prime minister last week.
By Republica

KATHMANDU, July 27: The government has claimed that fixing potholes and repairing roads inside the Kathmandu Valley has been expedited following the direction from the prime minister last week.


The Division Road Office, Teku, has submitted the progress report to the Prime Minister's Office mentioning the detailed condition of 22 various road sections inside the Kathmandu valley. According to the report, the repairing of bumpy roads inside the Valley will be concluded by the end of this month. 


“We have mobilized the agencies concerned on a war footing to fix the potholes, manage the dusty and muddy roads and maintain the roads after expansion,” said Joint Secretary at the Prime Minister's Office, Damodar Regmi. 


Related story

Kathmandu Road Division Office starts blacktopping road demolis...


Earlier, Prime Minister Sher Bahadur Deuba had instructed the three government secretaries concerned to fix the potholes of Kathmandu roads within 15 days on July 16.


The PM had issued the direction following the death of a school girl who was drowned in a sewage drain in Kathmandu.


“We have completed the maintenance of 60 to 70 percent of the problematic road sections by Thursday. We aim to make it 100 percent by Monday. If in case we can't, the process will not be stopped even after the deadline,” said Regmi. 


According to the progress report provided by the PM's office, the DAO has claimed that the condition of various 17 road section is in good condition. The office has claimed that blacktopping or graveling of most of the bumpy road section is underway and is expected to conclude by the end of this month. 


“Kathmandu Upatyaka Khanepani Limited and Department of Water Supply and Sewage have been asked to fix the sewage leakage in 22 places inside Kathmandu by Monday,” said Joint Secretary Regmi. 


The office has mobilized separate teams comprising an engineer, two sub-engineers and four to five length workers along with a mini dumper machine. 


DAO, Kathmandu Valley Road Improvement Project, Project Implementation Directorate and DAO Lalitpur have been working to repair the roads.  

Related Stories
SOCIETY

Traffic resumes after repair of collapsed road in...

SOCIETY

Daytime road repair causing huge traffic jams

SOCIETY

Govt extends Yeti Air crash probe deadline by 45 d...

POLITICS

Nepali Army faces risk of losing Rs 3 billion due...

SOCIETY

Repair of Nepal-India border posts begins