Published On: January 7, 2021 07:00 PM NPT By: Republica | @RepublicaNepal
KATHMANDU, RSS: Eighty-five per cent of the reconstruction of Kasthamandap has been completed so far. The remaining 15 per cent reconstruction works would be over by May this year.
Preparations are on at present to construct the roof of the historical monument after the construction of other structures.
Kasthamandap Reconstruction Committee Chairman Rajesh Shakya said they are preparing to bring the timber for the construction of the roof of this ancient temple from Rautahat district in the Tarai following shortage of timber here.
He said works are being done with the target of completing the reconstruction by May this year. According to Shakya, they are bringing 2,000 cubic feet timber from Rautahat within the next one month.
Although 8,000 cubic feet timber is necessary for the construction of the roof, the Committee is bringing only 2,000 cubic feet for now.
Then king of Kathmandu, Laxmi Narsingh Malla, had commissioned the construction of the Kasthamandap during the seventh century. The Kasthamandap is believed to have been constructed using the timber from a single tree. The name of the place Kathmandu has its origins in Kasthamandap.
Kasthamandap was completely destroyed by the Gorkha Earthquake in April, 2015. The deadline for the reconstruction of this historical heritage is three years.
The reconstruction cost is estimated at Rs 190 million. Of this cost, the Kathmandu Metropolitan City has already provided Rs 55 million to the Reconstruction Committee.
It is said altogether 17,056 cubic feet timber will be required for the reconstruction of the Kasthamandap.
The credit for the success of reconstruction process solely goes to the earthquake survivors themselves who managed the money by... Read More...