PHALEBAS (Parbat), Oct 6: Left in dilapidated condition for around a decade, construction of the Kaligandaki Highway that links Indian border in South and Korola border with China in North has been expedited.
Included in the list of national pride project, construction works to open and upgrade around 68 kilometres track from Kushma to Mirmi of Syangja have been speeded up, said the contractor RK Thapa.
Other works involve the widening of the road, the construction of gabion boxes and culverts among others.
Aimed to complete it by the Nepali month of Asadh end of 2074, Rs 390 million has been released so far for the constructions, a concerned authority said.
Two construction companies—Kasthamandap Construction Company and Surya Construction Private Limited—are engaging in the construction. RSS
GULARIYA, Oct 1: Prime Minister Pushpa Kamal Dahal on Saturday said the construction of the Postal Highway would be expedited. ... Read More...
NAWALPARASI, May 26: The construction of the Sub-station under the Kaligandaki Transmission Corridor project in Surya Basti of Sunawal municipality-13... Read More...
BANKE, Jan 19: After Minister for Physical Infrastructure and Transportation Ramesh Lekhak laid the foundation of Postal Highway on Wednesday, locals... Read More...
Leave A Comment