Kulekhani II resumption uncertain
MAKWANPUR: The resumption of Kulekhani-II Hydropower project at Bhainse VDC-1 in Makawanpur is likely to take more time. Kulekhani officials had assured that the plant would resume electricity generation within 10 days of the fire incident. The 32 megawatts Kulekhani has halted power generation for the last several weeks as two transformers of its three transformers were damaged in a fire that broke out on April 16. According to officials, it would take about a month to repair the damaged transformers. “It may take another three weeks to repair the transformer,” said engineer Ramesh Tiwari.