Message from Arun-3 Financial Closure

February 24, 2020 10:23 am

The 900MW Arun-3 Hydropower Project accomplished its key milestone—Financial Closure (FC) on February 6, 2020. A consortium of seven banks, including two Nepalese banks—Nabil and Everest—put a total of NPR 101 billion to the project, which has the total investment of approximately NPR144 billion. With the FC, the project has guaranteed its financial capability and we will witness its commercial operation by 2023 given any technical hitches don’t stall its construction. Arun-3 has become the largest project in terms of capacity and investment in Nepal.

Arun-3 achieves financial closure

February 7, 2020 09:52 am

KATHMANDU, Feb 7: The long-awaited Arun-3 Hydropower Project has finally achieved financial closure.