NA opens passage for Kaligandaki Corridor

alt=
Republica Locals welcome transport service in the newly opened Kaligandaki Corridor Highway in Gulmi.
By No Author
GULMI, Oct 16: The Nepal Army (NA) has successfully opened a 42-kilometer passage of the proposed Kaligandaki Corridor Highway in Gulmi district. The task has been dubbed as a project of national pride. The newly-opened passage starts from Ridi-Rudrabeni and ends at Palung Khola of Khadkot in Gulmi.

Construction of the 42 km track that began on May 18, 2013 has cost Rs 416.4 million, according to Colonel Resmi Raj Bhattarai, chief of NA construction taskforce in the district. "We have been working on Maldunga-Takure section in Baglung as well," he informed.


"Additionally, decision has been taken to construct road from Palung Khola to Takare of Baglung. It is just awaiting budget allocation, which may cost about Rs 330 million," added Bhattarai. The NA has so far spent Rs 566.4 million in the project.

The government had allotted the project to the NA as it seemed to be impossible to bring down rocks and hills along the Kaligandaki corridor without the army's expertise. The NA has been using explosives to blast hard rocks in the area. It cost Rs 58 million for the army to blast a seemingly impregnable cliff in Gulmi alone to open the track.

According to the NA, the army's unit had to toil hard to open the track at Bakewa cliff, Bargare cliff, Thapani cliff, Latre cliff, Bagdikhola cliff, Mauri cliff along with many others places in the 42-kilometer section.

The total length of the corridor is 369 km and the proposed highway connects Gaidakot of Nawalparasi district in the south to Palpa, Gulmi, Baglung, Myagdi, Mustang in the north. The highway also links China and India.

Tika Ram Dhakal, spokesperson of Central Stakeholder Committee of the Kaligandaki Corridor claimed that the road section in Gulmi, which covers 42 km, will be the shortest and easiest road linking China and India.

Apart from 22 km section of Palung Khola to Takare of Baglung, all other tracks of the Kaligandaki Corridor project have been opened.



Related story

Revised interest rate corridor system introduced

Related Stories
SOCIETY

Landslides blocks Kaligandaki corridor

Kaligandakiroadcorridor_20230630122433.jpg
SOCIETY

Landslides blocks Kaligandaki Corridor

duUoSW0B4vex0sUy7l4dR4VMoMjhrTbmJ2upsZXQ.jpg
SOCIETY

Kaligandaki Corridor remains blocked for three day...

Kaligandakicorridor_20240702111858.jpeg
SOCIETY

Landslide obstructs vehicular movement along Kalig...

Kaligandakiroadcorridor_20230630122433.jpg
ECONOMY

Kaligandaki Gorge Hydropower secures Rs 29.5 billi...

Qx5p57vrsmHFb3H7rnjqhMJS1Xj65GKzYaSwgDW7.jpg