Motihari-Amlekhgunj pipeline laying works affected

BIRGUNJ, Aug 1: Incessant rainfall has affected the installation of petroleum pipelines from Motihari of India to Amlekhgunj of Bara.
By No Author

BIRGUNJ, Aug 1: Incessant rainfall has affected the installation of petroleum pipelines from Motihari of India to Amlekhgunj of Bara. 


Laying pipeline has been so far completed in 15 kms out of 70 kms petroleum pipeline. The works have been heavily disturbed due to frequent rainfall. 


Related story

Only 12.2 km remain for laying fuel pipeline of Motihari-Amlekh...


It may be noted that Prime Minister KP Sharma Oli and his Indian counterpart Narendra Modi had jointly inaugurated the Motihari-Amlekhgunj petroleum pipeline from Haidarabad House in New Delhi during Nepal PM's state visit to India on last April. 


The pipeline construction is underway at the cost of Rs 2.75 billion. The Indian government has pledged to aid Rs 2 billion while Nepal is investing Rs 750 million for the project. RSS

Related Stories
ECONOMY

Nepal Oil Corporation finalises alignment for layi...

SOCIETY

Work of laying petroleum pipeline completes, ready...

ECONOMY

Cross-border petro pipeline-laying on full swing

ECONOMY

Nearly 50 percent of petroleum pipeline works comp...

ECONOMY

Cross-country petroleum pipeline test goes success...