ILAM, Nov 23: Residents of Ilam have urged the government to fast-track a new construction contract for the Belase–Golakharka section of the Mechi Corridor after the former contractor challenged the termination decision in court, raising fears of another prolonged delay.
The contractor failed to complete even half of the 9.5 kilometre road section within five years, despite receiving a two-year deadline and multiple extensions. The Road Division Office published the contract termination notice on October 29. The company subsequently approached the Patan High Court, seeking an interim order against the decision.
The legal dispute has alarmed residents, who fear a repeat of the four-year delay that affected the Damak–Chisapani road project due to court proceedings.
Also known as the Ilam–Jhapa Fast Track, the road is expected to provide an alternative route between the Tarai and the eastern hill districts. The Mechi Highway's Rajduwali section frequently gets blocked by monsoon landslides, leaving Ilam, Panchthar and Taplejung with limited road access.
Mai Municipality Mayor Khamba Singh Limbu said the unfinished road was causing hardship for residents and financial losses to the state. Once completed, it would cut travel distances between the Tarai and the hills by more than half, reducing fuel consumption, transport costs and travel time.
UML leader Nemwang and Khanal cast their votes in Ilam (Photo f...
He called on authorities to begin a fresh procurement process, saying the region could not afford further delays.
Ilam Municipality Mayor Kedar Thapa said the Belase–Golakharka section remained incomplete even as construction on other sections of the Jhapa–Ilam road approached completion. He warned that failure to start a new contract immediately could disrupt transport links to Ilam, Panchthar and Taplejung during the next monsoon.
District Coordination Committee Chief Jayaprakash Rai said residents had repeatedly complained about the slow progress, while elected representatives had also faced criticism over the stalled project. Despite repeated requests to the contractor, construction failed to pick up pace.
Rai warned that another monsoon without an alternative road could leave the hill districts cut off from the Tarai. He cited the Damak–Chisapani project as an example of the difficulties caused by prolonged legal disputes. A fresh procurement process for that road has now begun.
The concern stems from previous disruptions. Landslides at Rajduwali in October 2024 and October 2025 blocked road access to the three districts for months. Supplies of essential goods were disrupted, while agricultural produce worth millions of rupees spoiled because farmers could not transport it to markets. The unfinished fast track could not be used as an alternative because of its muddy condition.
Grishma Subba, chairman of Purbeli Jeep and Taxi Sewa Pvt Ltd, said the districts could face even worse transport problems next monsoon if the road remained incomplete.
The Road Division awarded the Rs 272.15 million contract on July 13, 2021, with a 30-month completion period. Despite a 33-month extension, the project had achieved only 45.28 percent financial progress and 47 percent physical progress by mid-November 2026.
The division said repeated extensions and written and verbal warnings failed to secure the contractor's promised progress, leaving termination as the remaining option.
Minister for Infrastructure Development Minister Sunil Lamsal had directed officials to terminate the contract during his visit to Ilam in July. The contractor was subsequently given a final deadline until the end of October after submitting a written commitment to complete the work.
Under the commitment, it was supposed to clear muddy sections within 20 days and finish blacktopping by the end of October. However, only minor work to fill muddy stretches was carried out before the company sought another extension.
After announcing the termination on October 29, Lamsal pledged to arrange the necessary funding and multi-year contract approval to launch a new procurement process immediately. The announcement initially raised hopes among residents, but no fresh tender has been initiated.
Meanwhile, nearly Rs 200 million allocated to the project has gone unspent and been frozen over two fiscal years because of construction delays.