NAWALPUR, Dec 27: The task of blacktopping in the eastern section of the Narayanghat-Butwal road stretch along the East-West Highway has gained momentum.

KATHMANDU, Nov 24: The Asian Development Bank (ADB) project directorate has warned the contractor company of the Narayanghat-Butwal road section to terminate the contract if the overall physical progress of 50 percent is not achieved by December 2023.

MADHYABINDU (Nawalparasi), Oct 12: The eastern section of the Narayanghat-Butwal road expansion project has so far witnessed sluggish physical progress.

NAWALPUR, Sept 26: As the construction works along the Narayanghat-Butwal road section of the East West Highway remained intolerably slow, the government has warned the contractor of contract termination.