header banner
SOCIETY

Wire extension on Trishuli-Kathmandu 220 KV transmission line begins

BETRAWATI, Oct 24: Wire expansion has begun along the under-construction Trishuli-Kathmandu 220 KV ‘Double Circuit’.
By No Author

BETRAWATI, Oct 24: Wire expansion has begun along the under-construction Trishuli-Kathmandu 220 KV ‘Double Circuit’. 


The wire is being installed on the electric poles from Suryamati to Thansingh of Nuwakot since Tuesday, shared Upper Trishuli Three ‘A’ Hydropower Project Chief Fadindra Raj Joshi. 


Related story

Dana-Khurkot transmission line and substation ready


He further said the contractor company – China International Water and Electric Corporation – has started extending electric wires from Suryamati to Thansingh via Chaturale in the first phase. 


The electric wire installation has taken momentum after the task of erecting poles along the transmission line has come to a final stage. Almost seven years ago, the construction of the transmission line had started so as to connect electricity generated in Nuwakot and Rasuwa to central power grid. 


Most of the 140 electric poles located along the transmission line have been erected and remaining poles are yet to developed and erected, informed Deputy Manager of the Project, Satyaram Jyakhwa. 


“The construction of transmission line seems to be completed in the stipulated date with the resolve of problems such as resistance from locals on the construction of line, delay in determination of compensation and consumption of community forestry”, he added. 


RSS

Related Stories
ECONOMY

Markichowk 220 kV substation and Marsyangdi-Kathma...

ECONOMY

Kushma-New Butwal 220 kV transmission line comes i...

ECONOMY

Chilime-Trishuli transmission line construction de...

ECONOMY

First phase construction of Koshi Corridor 220 KV...

SOCIETY

Test transmission of Khimti-Dhalkebar transmission...