The breakthrough of the Mahadevtar tunnel on Wednesday marks a significant engineering achievement for the Kathmandu-Tarai Fast Track. But the occasion has also raised an uncomfortable question: How can a national pride project remain only about 50 percent complete after 12 years, despite billions of rupees in public investment and years of construction under the Nepali Army? The 3.422-kilometer tunnel is the longest on the 70.977-kilometer expressway connecting Khokana in Lalitpur with Nijgadh in Bara. It also lies along one of the project's most technically challenging sections. However, the breakthrough should not distract from prolonged construction, rising costs and repeated deadline extensions. Originally envisioned as a four-year project, the Fast Track was expected to provide a direct and shorter connection between Kathmandu and the Tarai. The government handed construction responsibility to the Nepali Army in 2017. Since then, the authorities have revised the completion target several times. The November 2024 deadline was first pushed to April 2027, and the latest extension has further postponed completion until April 2030. Twelve years after the project began, another three years are being sought to finish the remaining work. Repeated revisions of the deadline raise questions about the quality of project preparation and the government's ability to manage large infrastructure schemes. The challenging terrain and the need for specialized engineering were known from the outset. The 11.2 kilometers of tunnels and 89 bridges should have been constructed according to the original plans, cost estimates and schedule.
'Project specific bond could be issued to finance fast-track ro...
The repeated deadline extensions suggest that the authorities either underestimated the challenges or failed to address them in time. The Khokana dispute is one such challenge. The proposed starting point at Khokana in Lalitpur has remained contentious over land acquisition, compensation, Guthi land and cultural heritage. Since local discontent and resistance cannot simply be dismissed as obstacles to development, the government should have pursued consultations and a workable settlement with local people much earlier. The prolonged dispute with Khokana residents has exposed poor coordination among the authorities and agencies responsible for delivering this major project on time. The financial side of this national pride project is equally worrying. The estimated project cost, including VAT, has climbed to Rs 211.93 billion, while expenditure had reached Rs 94.22 billion by August this year. Rising construction costs, prolonged contracts and changes in project requirements have added pressure on public finances, with each additional year risking further escalation. The government must explain how much of the cost increase is attributable to inflation, design changes, compensation and construction delays. Without such an accounting, the public cannot determine whether the additional spending reflects unavoidable engineering costs or weaknesses in project management. Progress across the various construction sections and packages has been uneven. Although breakthroughs have been achieved in the Dhedre and Lendanda tunnels, finishing works are still underway. Construction continues on the Chandram Bhir, Sisautar, Devichaur and Mauribhir tunnels. Contracts have been awarded for 85 of the 89 bridges, but only five have been completed.
The government's dissatisfaction with packages 9A and 8B indicates that contractor performance remains a serious concern. Minister for Physical Infrastructure and Transport Sunil Sharma has warned that contracts could be terminated if contractors unnecessarily prolong construction. Such warnings must be backed by firm decisions and clear performance assessments. The Nepali Army deserves credit for advancing technically demanding sections and achieving several tunnel breakthroughs. However, assigning construction responsibility to the Army does not absolve the government of its duty to monitor expenditure, resolve administrative bottlenecks and ensure timely delivery. Political leadership remains accountable for the project's overall direction. Delays are particularly costly given the expressway's strategic value. Kathmandu depends on existing highways, including the Prithvi Highway and Tribhuvan Highway, for road access to the southern plains. However, landslides, floods, accidents and road closures frequently disrupt passenger and cargo movement. Once completed, the Fast Track will provide an alternative to these highways, reduce travel time and improve the movement of goods between the capital and the Tarai. But the country cannot reap these benefits until the expressway is fully operational. The government must therefore turn the latest tunnel breakthrough into renewed momentum and ensure that the project faces no further unnecessary delays.