Government extends project deadline till 2030
KATHMANDU, Nov. 18: The Kathmandu-Terai Expressway (Fast Track), one of Nepal's flagship national pride projects, marked a major milestone on Wednesday with the breakthrough of its longest tunnel at Mahadevtar in Makwanpur district. However, the overall progress of the project stands at only around 50 percent, despite 12 years having passed since its inception.
President Ram Chandra Paudel officially inaugurated the breakthrough of the 3.422-kilometre Mahadevtar tunnel. The 70.977-kilometre expressway, stretching from Khokana in Lalitpur to Nijgadh in Bara, includes a total of 11.2 kilometres of tunnels.
Despite nine years of construction under the management of the Nepali Army, the project's physical progress has reached only about half of the planned works. Initially scheduled for completion by November 2024, the project failed to meet the deadline and was subsequently extended until April 2027.
Fast track construction works moving ahead satisfactorily
Citing slow construction progress and multiple challenges, authorities have further extended the completion deadline to April 2030. A longstanding dispute over land acquisition in Khokana, which has plagued the project since its early stages, remains unresolved.
The cost of the strategically significant project has also continued to rise amid delays. The total estimated cost, including VAT, has reached Rs 211.93 billion. As of August this year, Rs 94.22 billion had already been spent on construction works.
According to the Nepali Army, construction is underway on seven tunnels along the expressway. Breakthroughs have already been achieved in the Dhedre and Lendanda tunnels, measuring 1,691 metres and 1,623 metres, respectively, with finishing works currently in progress.
Construction of the Chandram Bhir Tunnel (2,237 metres), Sisautar Tunnel (390 metres), Devichaur Tunnel (1,000 metres) and Mauribhir Tunnel (583 metres) is also progressing at various stages.
The expressway project includes 89 bridges, of which contracts have been awarded for 85. Five bridges have already been completed, while several complex structures reaching heights of up to 82 metres have been built.
While President Paudel and the Nepali Army described the project as progressing rapidly, the government expressed dissatisfaction with the pace of construction.
Addressing the breakthrough ceremony, Minister for Physical Infrastructure and Transport Sunil Sharma said the Nepali Army should complete the remaining works within a maximum of three years.
According to the minister, progress on packages 9A and 8B remains unsatisfactory. He warned that the government could no longer tolerate further delays and urged the Nepali Army to terminate contracts where contractors were found to be unnecessarily prolonging work.