Sunkoshi-Marin diversion: 12-km tunnel-digging completed, breakthrough in sight

KATHMANDU, March 22: The tunnel digging process of Sunkoshi-Marin Diversion Project has made spectacular progress.
By Republica

KATHMANDU, March 22: The tunnel digging process of Sunkoshi-Marin Diversion Project has made spectacular progress. 


Prime Minister Pushpa Kamal Dahal has shown regular interest in the project having the goal of providing irrigation in Terai Madhesh within 12 months. 


According to the project, the tunnel digging will be completed within the next one-and-a-half months if there is no geographical complication. 


Related story

Sunkoshi-Marin Diversion Project’s tunnel construction nears co...


Chief of Sunkoshi-Marin Diversion Project, Mitra Baral shared that out of the total 13.3 kilometers long tunnel, a 12.79 kilometers section has been constructed so far. 


"Tunnel-digging has seen significant progress. If there is not any physical complication, we are preparing to make a breakthrough within the next one and a half months," Baral said. 


Minister for Energy, Water Resources and Irrigation Shakti Bahadur Basnet had instructed the project chief and other officials not to leave the project site and fix the problems at the local level. 


While both time and costs are increasing in most of the projects of national pride in the country, the diversion project has attracted the attention of many at the moment. 


RSS


 

Related Stories
Editorial

Taking Nepal into the tunnel era for economic pros...

ECONOMY

PM Oli to open breakthrough of BBDMP’s tunnel cons...

ECONOMY

Lendanda tunnel of Kathmandu-Madhesh Expressway ma...

ECONOMY

Nagdhunga-Naubise tunnel route to undergo breakthr...

ECONOMY

Rasuwagadhi Hydropower Project achieves tunnel bre...