SC gives mandamus order to stop carrying out physical works in Mistri Khola hydel project

KATHMANDU, Jan 29: The Supreme Court (SC) has issued a mandamus order to immediately halt the physical infrastructure of the under-construction Mistri Khola-2 hydel project in Myagdi district.
alt=
By RSS

KATHMANDU, Jan 29: The Supreme Court (SC) has issued a mandamus order to immediately halt the physical infrastructure of the under-construction Mistri Khola-2 hydel project in Myagdi district. 



A division bench of justices Kumar Regmi and Mahesh Sharma Poudel issued the order on Sunday stating that the construction works of the hydel project would pose an irreparable loss to Tatopani kunda (a hot water spring). 


Related story

11 bridges built, 2 under-construction on Pokhara-Muglin road


Earlier, the court had scrapped the preliminary environmental impact assessment citing that the project would have a direct impact on the source of the hot water spring. 


Eighteen local people including Rum Lal Pun, Khimmaya Tilija and others had filed the petition at the SC stating that development of the project there would result in drying up of the hot water spring and would cause serious environmental impacts there.


 

Related Stories
ECONOMY

Mistri khola hydro project to generate power in a...

Mistri khola hydro project to generate power in a month
WORLD

Desperate search for missing girls as nearly 80 de...

6gF0nzTAaWVBgM9MsMUl0qcLxxCVrjdLcvk7UYJY.jpg
ECONOMY

12 years on, Darkhe Khola hydro project still inco...

Darkhe-Khola-Laghu-Hydropower-Project_mugu_20200216110840.jpg
ECONOMY

Preparatory work of Inkhu Khola, Lower Hongu Khola...

Preparatory work of Inkhu Khola, Lower Hongu Khola to be completed by mid-July
SOCIETY

Prithvi Highway to close from 10PM to 3AM until Ju...

1683106470_PrithiviHighway-1200x560_20230503155423.jpg