KATHMANDU, May 15: The process to construct the proposed 400 kV new Butwal-Gorakhpur second transnational transmission line between Nepal and India has moved forward. The Nepal Electricity Authority (NEA) has got approval for foreign investment in the project.
Under the joint venture project of the NEA and the Indian Power Grid Corporation, a company will be established in India to do the construction work on the Indian side.
For it, the NEA has to manage Rs 736 million, which is 50 percent of the total budget. But, the NEA itself will bear the cost to construct the project on the Nepali side.
The double circuit transmission line is around 120 kilometers between New Butwal substation at Sunawal Municipality-13 in Nawalparasi district and Gorakhpur substation in India. Of the area covered by the project, around 20 kilometers fall in the Nepali side and the remaining in the Indian side.
Test transmission of Khimti-Dhalkebar transmission line begins
NEA Executive Director Kulman Ghishing said that the permission to NEA for foreign investment has paved the way for establishing a company in India on joint venture of NEA and Power Grid for the development of a project.
“An article of association and regulation have been readied for the company establishment and with the obtainment of a permit for an investment from India, the establishment of the company will be moved ahead,” he said.
It may be noted that the seventh meeting of a mechanism of Nepal-India energy secretaries and joint-secretaries on October 14, 2019 finalized the investment model for the development of the transmission line.
The estimated cost of the project is Rs 7.039 billion and the final management will be ensured through 80 percent loan and 20 percent equity.
Preparations for bid documents are going on for the selection of a project developer and we plan to complete in three years of its commencement.
The NEA and Power Grid in August-September 2021 signed a MoU for joint investment.
A Cabinet meeting on August 3 allowed the NEA for an investment of 50 percent share in the construction of the transmission line segment toward India.
Nepal will construct the part of the transmission line in Nepal on its own while the section in India will be constructed on the joint venture of NEA and Power Grid.
The transmission will have the capacity of supplying around 2,000 megawatts of electricity.