KATHMANDU, Nov 27: The 669 MW Lower Arun Hydropower Project is targeting to begin electricity generation on December 4, 2030, the Office of the Prime Minister and Council of Ministers said on Friday.
The information was shared during the office’s regular press briefing. Spokesperson Hriday Raj Aryal said the project had entered the implementation phase.
Prime Minister Balendra Shah and Indian Prime Minister Narendra Modi jointly laid the foundation stone for the project during Shah’s visit to India on November 22 and 23.
Solar power project in Butwal starts commercial power generatio...
Aryal said a contract worth approximately INR 11.4921 billion had also been invited for the project. He said construction would move ahead with the aim of meeting the scheduled power generation deadline.
At the same briefing, the Public Procurement Monitoring Office announced that it had decided to blacklist 20 firms and companies recommended by various public entities under prevailing laws.
The office has also provided advice to 23 public entities on construction and consultancy services. It has approved and brought into implementation the Procedure on Remuneration and Social Security of Workers Engaged in Public Procurement, 2083.
Aryal further said the Hello Sarkar grievance-handling system received 3,051 complaints over the past 10 days, of which 2,754 had been settled and 234 addressed.