Floods take 430 MW of electricity offline, damage 11 hydropower projects

Flooding in the Bhotekoshi River has taken around 405 megawatts of electricity generated by 11 hydropower projects offline from Nepal’s national power system, according to the Ministry of Energy.
alt=
By REPUBLICA

KATHMANDU, Aug 26: Flooding in the Bhotekoshi River has taken around 405 megawatts of electricity generated by 11 hydropower projects offline from Nepal’s national power system, according to the Ministry of Energy.



An additional 25 MW of solar power has also been affected by the floods, bringing the preliminary total of electricity knocked out of the system to around 430 MW.


Related story

Mandu Hydropower halts production as Bagmati floods cause struc...


The floods damaged hydropower projects and transmission infrastructure, disrupting both electricity generation and transmission and significantly affecting the national power system.


The ministry is collecting detailed information on the 11 affected hydropower projects, the extent of damage and the amount of electricity taken offline.


Further details are expected to be released later.


 

Related Stories
ECONOMY

Floods cause estimated Rs 74 billion damage to pow...

Bhote Koshi Flood-1788445897.webp
ECONOMY

NEA to make alternative arrangements for electrici...

NEA_20240109075208.jpg
ECONOMY

PTC India to buy electricity generated from Arun-I...

ArunIII_20220116114120.jpg
SOCIETY

Meta outage briefly takes Facebook and Messenger o...

Metaverse_20211219160535.jpg
WORLD

USAID website goes offline in Trump administration...

fKIpwbUjpRviT43EGRsoKAae8LJYhNpzJsyGLxXg.jpg