DANG, Nov 23: Construction of the four-lane road connecting two major cities in Dang, Ghorahi and Tulsipur, has resumed after years of delays, but progress remains slow, with only 17 percent of the work completed in the past 15 months.
The 21.58-kilometre road has been a major source of inconvenience for residents, remaining dusty during dry weather and muddy during the monsoon. Frequent accidents on the dug-up road have also claimed several lives.
Construction of the Ghorahi-Tulsipur road began in 2019 with a loan from India’s Export-Import Bank. India’s Tathya Engineering and Infra Project was initially awarded the contract but failed to complete the work, leaving the project stalled. The government terminated the contract in 2023.
A new contract was subsequently awarded to Diwa/Bandan Bhagwati JV, which resumed construction 15 months ago. The project has a total contract value of Rs 2.53 billion.
Locals enraged over snail-paced road construction
According to the Road Division Office, Dang, around Rs 379.5 million, or 15 percent of the contract amount, has been spent so far.
Road Division Chief Dipendra Bahadur Bista said the contractor had carried out earth cutting and constructed 38 box culverts along a 14-kilometre section from Ratanpur Chowk in Ghorahi to Beljhundi in Tulsipur. Three additional slab culverts are under construction, while six kilometres of concrete drains have been completed.
Gravelling is being prepared in sections where earth cutting, drainage and culvert work have been completed.
The relocation of electricity poles from Gurje Khola in Ghorahi-10 to Beljhundi in Tulsipur-18 has also been completed, while work is ongoing on the section between Ghorahi and Gurje Khola. Culverts and retaining walls are also being built in the area.
Bista said construction had been slower than expected due to the monsoon and the Dashain-Tihar holidays, but expressed confidence that work would accelerate now that the festive period was over.
Sunil Dhungana, contract manager of the construction company, said work was progressing according to the plan, despite delays caused by the weather and festivals. He said the company was carrying out earth cutting, filling potholes and building drains, walls and culverts.
“Work could not gain momentum because of the monsoon and the festive season. With the weather clearing and workers gradually returning, construction will now gather pace,” Dhungana said.
The contract was signed with the Kathmandu-based joint venture on July 8, 2025, with a three-year completion deadline. Construction resumed on November 17, 2025, and the road is scheduled to be completed by July 8, 2028.
Under the project, the road will be 30 metres wide in urban areas, including footpaths, with a 20-metre-wide paved carriageway. In rural sections, the paved road will be 15 metres wide, according to the Road Division Office.
The contractor has deployed around 40 vehicles and pieces of equipment, including excavators, graders, rollers, backhoe loaders, tipper trucks, trailers, cranes, tractors and water tankers. It has also installed a crusher plant, mobile screening plant, mobile sand washer, asphalt plant and concrete batching plant at its construction camp.