header banner
ECONOMY

Construction of Thamkhara airport delayed

KHOTANG, July 21: Negligence by contractors has left construction of Thamkharka airport in the eastern district of Khotang in quandary. The deadline to complete the work was mid-July, 2018.
By Republica

KHOTANG, July 21: Negligence by contractors has left construction of Thamkharka airport in the eastern district of Khotang in quandary. The deadline to complete the work was mid-July, 2018. 


According to the Civil Aviation Authority of Nepal (CAAN), only 75 percent of the construction work has been completed so far. The construction work was commenced in 2016, with a target to complete by mid-July 2018, according to project engineer Ratna Shrestha. 


Rauta Construction has undertaken the task of constructing the airport. The airport construction site is at Badkadiyale–4 in Khotehang Rural Municipality in the district. 


Although the airport was ready for blacktopping, early monsoon has affected construction works, Shrestha told Republica.


Related story

We will start construction of Nijgadh Int’l Airport soon: PM Da...


“Only the blacktopping work has remained at the airport,” Shrestha said. “The material needed for blacktopping has not been delivered yet.”


The CAAN had commenced the construction work with an investment of Rs 92.5 million. 


Locals have complained that the contractors have been dillydallying with the construction work. The District Administrative Office has reported to the Ministry of Home Affairs about the delay in blacktopping at the airport.


As the construction work continued to get delayed, the contractor had amended its work schedule on January 22 this year. According to the new schedule, the contractor was supposed to complete asphalt concreting by mid-June, and complete the entire work by mid-July. 


“As soon as the rains stop, we will resume work and complete it within two months,” Shrestha claimed.


Delay in the construction of the only airport in the southern part of the district has angered the people of Khotehang, Barahapokhari and Jantedhunga Rural Municipalities. 


The airport is providing air services to the people of Khotehang, Barahapokhari, Jantedhunga rural municipalities of the district, as well as several villages of neighboring Bhojpur district. It is the only option for public transportation due to lack of road connectivity. Previously, the airport used to operate round the year. 


The airport had halted its operation along with the beginning of blacktopping work at the airport on March 13, 2017, according to Narendra Udas, station in-charge of the airport. 


Rauta construction has sub-contracted the blacktopping work to a private contractor, Mahesh Regmi. The CAAN had allocated Rs 55 million for the blacktopping. 

Related Stories
SOCIETY

Construction of bridge over Tawa River in Khotang...

POLITICS

Lawmakers blame delayed construction behind growin...

ECONOMY

Middle Modi hydro project further delayed

ECONOMY

Feasibility report of larger Dharan Airport ready

Editorial

Take holistic approach to build Nijgadh Int’l Airp...