SINDHUPALCHOWK, July 15: Melamchi Drinking Water Project is set to miss its third deadline as only half of the total 26.5 kilometers pipelines for the project have been laid so far.
The latest deadline, which was extended for the third to mid-2016, will expire in less than 14 months.
Here’s what Miss World 2019 Toni-Ann Singh is doing in Helambu...
The first deadline for the drinking water project, which is expected to supply 170 million liters of water on a daily basis, was set for 2007. But 15 years after the deadline expired, the project is yet to accomplish its goals.
Even to this day the authorities can not definitively say when the Melamchi project will be completed.
Ghanashyam Bhattarai, executive director of Melamchi project, blamed the contractor for delaying the project.
After China Railway 15 Bureau Group Corporation left the project midway completing 6.5-km tunnel in three and half years, the contract was awarded to an Italian contractor Cooperative and Muratorie Cementisti di Ravenna (CMC). It had agreed to complete digging of 26.5-km tunnel in five years.
But CMC has already missed the deadline as per Melamchi Water Supply Development Board (MWSDB).
Although construction works, briefly stalled following the April 25 earthquake, has resumed, the task has been mostly limited to removing the obstructions caused by the disaster. The project team has not even conducted the assessment of the full extent of the damage caused by the earthquake.
"A technical team has started assessing the damage within the tunnel," said executive director Bhattarai.
In order to complete the project within 14 months, the Italian contactor will have to dig tunnel at the rate of 1 km per month.
Over Rs 7 billion has already been spent to implement the project.1970
- Acute shortage of drinking water
- Formation of Drinking Water and Drainage Management with a view to improve distribution of drinking water facilities
1988
- Identification of drinking water sources assigned to British Company. Melamchi was the first priority among 20 alternatives
1997
- Establishment of Melamchi Water Limited
1998
- Feasibility study for Melamchi project by the companies including Spray Mountains of Australia.
- Detailed survey carried out by Narplant
- Formation of Melamchi Water Supply Development Board (MWSDB)
2000
- Melamchi Drinking Water Supply Project started
- Agreement between Asian Development Bank and MWSDB for 120 million US dollar loan
2007
- First project deadline
2008
- Restructuring of project
2009
- Agreement with China Railway 15 Bureau Group Corporation for digging out 26.5-km long tunnel for the project
2012
- China Railway 15 Bureau Group Corporation stops work
- Project agreement canceled on September 25, 2012
2014
- Contract awarded to Italian contractor Cooperative and Muratorie Cementisti di Ravenna (CMC)
2016
- Third deadline of Melamchi project