KATHMANDU, Feb 25: Tanahun hydropower project, the second storage project of the country, has witnessed 51.44 percent of its physical progress.

DAMAULI, May 8: As many as 32,000 towers have been installed for the construction of transmission line of the 140 MW Tanahun Hydropower Project

TANAHUN, Nov 17: The work of digging a 560-meter-long section of the tunnel toward the power house of Tanahun Hydropower Project has been completed. A total of 1,480 meters long tunnel has to be dug.

KATHMANDU, July 8: Four different companies have come up with formal intent for the construction of structures, including a dam in Tanahun hydropower project. Four companies, including a consortium of Nepali entity, have submitted quotations for the construction of different structures in the 150-MW Tanahun Hydropower Project.

DAMAULI, Oct 5:  Local people of Byas Municipality-5 in Tanahun affected by a hydropower project have voiced concerns about solatium issue.