DAMAULI, March 6: The rural electrification campaign is taking place in different areas of Tanahun district where substations for power supply are being constructed. The substations are being built with support from the Tanahun hydropower project for the electrification drive.
Managing Director of Tanahun hydropower project Kiran Kumar Shrestha said that the substations are completed in Ghiring Rural Municipality-4 and Bandipur Rural Municipality-6.
Two electricity distribution substations inaugurated
After the construction of the substations, power supply has been ensured to Bhimad Municipality, Ghiring Rural Municipality and Rising Rural Municipality in Tanahun, and some parts of Nawalparasi (Bardaghat Susta east).
The officials have claimed that reliable and quality power supply is guaranteed to the consumers.
Managing Director Shrestha shared that the campaign of rural electrification would be completed in the upcoming fiscal year.