GULMI, Aug 28: The motorway along the Ridi-Rudrabeni-Bamitaksar road stretch has resumed operation after remaining shut for the last one month.
The road shutdown after swollen Badighat river eroded 700 metres of road stretch a month ago.
Transportation resumed after a kilometer of alternate route was constructed near Urlikhola area and expansion of the road network at Cisne area of Rupakot took place, according to Tamghas Simaltari Road Project's sub-engineer Dinesh Ojha. RSS