83 percent construction of Postal Highway completes in one and half decades

Published On: January 13, 2023 12:00 PM NPT By: Republica  | @RepublicaNepal


KATHMANDU, Jan 13: Around one and a half decade into construction, 83 percent work on the Postal Highway has been completed. It will take around three more years for the national pride project to complete, it has been said. 

Under the project considered to be a base for the prosperity of the Terai Madhesh, construction of 910 kilometers of road and 115 bridges have been completed. 

The COVID-19 pandemic, disputes related to the project location and the border blockade are blamed for the delay, said Dharmendra Kumar Jha, chief of the Postal Highway Directorate. The construction of around 250 kilometers of road has yet to be contracted, and work on around 500 kilometers is underway, said the directorate. 

Negligence of the contractors in some cases is blamed for the delay, said Jha, adding that in some other cases, the contract was extended from time to time. 

Chief Jha said although there was an arrangement to extend the deadline in the past, now construction companies could be fined for their failure to complete the works within the deadline. 

Now, around 500 km of road is under construction under the project. According to the directorate, the contract would be canceled if works are not carried out as per the schedule. 

According to the project, a target has been set to construct 27 bridges and to blacktop 160 km of road in the current fiscal year. 

The latest deadline has been extended till current fiscal year 2022/23. Chief Jha said COVID-19 has affected this project like many other development projects.

 


Leave A Comment