The CIAA acted after forming a task force, following complaints of increasing explosion of transformers, interrupted supply of electricity, half voltage and the delay in the maintenance or repair of broken down transformers, wires and other equipments among others.
The study was conducted in 10 locations in the valley.
According to available data, in the past six months along, the total 406 transformers were exploded in the valley and 3,888 aerial bundled cables damaged due to overuse of electricity, following Indian unofficial border blockade. RSS
‘Illegal’ private transformers troubling pedestrians