KATHMANDU, Nov 23: The construction of Dhalkebar-Muzaffarpur cross-border transmission line to import 90 megawatts of electricity by December this year has been halted yet again.

The Nepal Electricity Authority (NEA) had planned to import 90 MW of electricity by installing conductor of 132 KVA capacity. NEA was hopeful that import of power from India would aid to reduce load shedding during the winter season.

“The work had resumed some time ago after seeking approval from agitating parties and contractor,” said Chief of Power Transmission Company Nepal (PTCN) Ashok Kumar Pandit, “But, excavator operators have denied working fearing attack from protesters.”

According to him, the work will resume again if situation normalizes in a day or two.  Out of 113 transmission towers in Nepali side, only five are left to be constructed.



Related story

Civic leaders for addressing Madhes issues before elections

Related Stories
ECONOMY

China hints at buying Nepali tea as India prepares...

illam-tea.jpg
ECONOMY

Food Management and Salt Trading Corporation to im...

wheat_20220825184809.jpg
POLITICS

Naming Province 2 as Madhes Province honors Madhes...

1630075771_upendrayadav-1200x560_20211113160550.jpg
ECONOMY

Import ban results in closure of 58 motor dealers...

CarHandover_20220422192316.4jpg
ECONOMY

Auto-rickshaw imports through Birgunj doubles in f...

Tempo-Import.jpg