The Ministry had carried out the projects of lessening the load shedding within three years with a slogan of Bright Nepal: Prosperous Nepal. However, the economic survey of the government reads that the constructing projects did not get success as per the plan and expectation.
Only the construction work of Upper Tamakosi Hydropower was found effectively run while other national pride projects were not accelerated as per the expectation.
The survey further reads that the projects Upper Trishuli 3A, Rahughat, Chameliya and Kulekhani Third run by the Nepal Electricity Authority (NEA) were moving ahead in a sluggish manner.
The capital expenditure of the Ministry was only around 40 per cent. Though the Ministry was searching for alternative measures to lessen the power shortage, it is yet to materialize in reality. However, works of the Dhalkebar-Mujaphphar 400 KV transmission line is in last stage. With the completion of the project 150 mega watt power could be imported from India.
Similarly, a quotation has been called for setting up solar energy plant of 25 megawatt in the capital.
Similarly, a joint taskforce of Nepal and India was working for preparing detail project report (DPR) of Pancheshwor Multipurpose Project.
With the completion of the DPR, the project is expected to accelerate. Similarly, discussions were underway with The Three Gorges, Chinese company for the construction of West Seti Hydro Project.
ADB-financed projects continue to move at sluggish pace
The Investment Board has also approved to call international donors for the construction of the project.
The government has expected to accelerate the projects by removing the obstacles seen in the policy level in the coming years. RSS