KATHMANDU, Nov 26: Three months have passed since devastating floods struck the Bhotekoshi and Trishuli rivers on August 26. The disaster caused unprecedented loss of life and property, damaging infrastructure across riverside areas of Rasuwa, Nuwakot, Dhading, Gorkha and Chitwan districts.
Yet even after three months, long-term reconstruction and the permanent resettlement of affected families have failed to make the expected progress.
The government launched rescue, relief, rehabilitation and reconstruction efforts after the fast-flowing floods destroyed settlements, roads, bridges, electricity infrastructure and hydropower projects.
However, local residents in Nuwakot complain that while immediate relief and administrative support have been provided over the past three months, long-term reconstruction has made little progress.
Arpit Khadka of Angaputar, Ward 9 of Bidur Municipality in Nuwakot, said only two Bailey bridges, one each at Betravati and Devighat, had been built during the three months. Work had also been limited to opening a temporary road track from Dhunge Bazar to Betravati, he said.
A suspension bridge has been constructed upstream of the site where the building of the Trishuli Hydropower Centre was washed away, providing a crossing over the Trishuli River from Bidur 1, the district headquarters of Nuwakot, he added.
Khadka said the failure to rebuild roads and bridges at the expected pace had made it difficult for flood-affected residents to sustain their livelihoods.
Although the suspension bridge has made it somewhat easier for pedestrians to cross the Trishuli, locals continue to face considerable hardship because construction of the Bailey bridge at Trishuli Bazaar, which was supposed to be completed by November 16, remains unfinished.
Shree Krishna Dangol of Betravati also said the slow pace of road and bridge construction following the floods had made daily life extremely difficult for local residents.
Most residents of Rasuwa and Nuwakot have faced similar problems because of delays in infrastructure reconstruction. The government has repeatedly said it would complete the reconstruction of flood-damaged infrastructure as soon as possible and reopen the Rasuwagadhi customs point on the border with China.
Although the government has distributed relief to flood affected communities, collected details of affected families, identified land for resettlement, restored electricity supply, provided tax and loan concessions to businesses and mobilised international assistance, infrastructure reconstruction has failed to advance at the expected pace.
Authorities, local communities pledge to help in Dharahara reco...
According to affected local governments, detailed assessments of needs in flood-hit areas, riverbank erosion control and temporary housing arrangements are under way. However, displaced families in Syafrubesi, Timure, Betravati, Nuwakot and Dhading are still struggling to survive in temporary camps and monasteries.
With no concrete long-term reconstruction plan being implemented and resettlement delayed, flood victims in Rasuwa, Nuwakot and Dhading have formed struggle committees to pressure all three levels of government to act.
The United Nations' Loss and Damage Fund has decided to provide Nepal with a grant of $20 million, equivalent to around Rs3 billion, to support work in flood-affected areas. The government plans to initiate the process of using the grant to rehabilitate affected communities.
The Ministry of Finance said the government had provided initial cash assistance to the affected districts over the past three months. According to the ministry, Rasuwa and Nuwakot each received RS 10 million, while Dhading received RS 5 million.
Similarly, RS 135 million has been provided to 15 affected local governments. A one-door system has been introduced through the Prime Minister's Natural Disaster Relief Fund to manage cash and in kind assistance received from various organisations.
The government has introduced 18 types of relief and concessions for industries, businesses and commercial establishments affected by the Bhote Koshi floods. These include extensions for filing tax returns, tax adjustments for damaged property, restructuring of bank loan principal and interest payments, concessional interest rate loans and assistance with insurance claim settlements.
The government has also fast-tracked a provision allowing insurers to make advance payments of up to 50 percent of the estimated claim amount for damaged physical infrastructure, based on preliminary assessments.
Efforts to identify land for the resettlement of affected families have also been accelerated. The government had formed a committee to identify and study potential land sites to relocate families who lost their homes in the floods to safer locations.
The committee has identified 277 land plots across Rasuwa, Nuwakot and Dhading, covering more than 3,279 ropanis. However, despite identifying potential sites, the permanent resettlement of affected families has yet to take place.
During this period, the government has also attempted to advance plans for integrated settlements equipped with roads, drinking water, electricity, schools, health facilities and communication services.
The floods damaged electricity transmission lines, poles, substations and distribution systems, disrupting power supply in Rasuwa, Nuwakot and Dhading.
The Nepal Electricity Authority and the Alternative Energy Promotion Centre worked to restore electricity supply. A total of 400 household solar power systems and 13 systems for office use were sent to affected areas.
After it became clear that electricity supply in Rasuwa could not be restored immediately, authorities identified 1,268 households and coordinated arrangements to provide alternative energy.
The government claims that electricity services have been fully restored in Dhading, while supply has gradually resumed in most areas of Rasuwa and Nuwakot.
To reopen transport routes, the Department of Roads and the Ministry of Physical Infrastructure and Transport began clearing landslides, opening single-lane tracks along damaged sections between Galchhi in Dhading and Rasuwagadhi, and repairing the Bidur to Betravati and Dhunge to Trishuli road sections. However, local residents say progress remains slower than expected.
The Bagmati provincial government has decided to allocate Rs6 billion for reconstruction and rehabilitation in Rasuwa, Nuwakot, Dhading and Chitwan.
Private sector seeks government facilitation
The Bhote Koshi floods caused severe damage to 13 hydropower projects, including Rasuwagadhi, Upper Trishuli 1, Trishuli 3A, Trishuli 3B, Chilime and Rasuwa Bhote Koshi. Electricity generation at these projects has come to a halt after mud, silt and rocks accumulated in their dams, powerhouses and tunnels.
Of the 13 affected projects, nine are privately owned, while the remaining projects are associated with the government or government-owned companies.
Although all nine privately owned projects have full insurance coverage, making financial reconstruction appear feasible, private sector energy producers say policy, legal and administrative complications have made it difficult to begin the work.
On Wednesday, private sector representatives urged the government to introduce tax exemptions, customs concessions, extensions of project licences and special policy arrangements for importing repair equipment and materials.
Mohan Kumar Danghi, president of the Independent Power Producers' Association, Nepal (IPPAN), drew the government's attention to the problems facing the sector. He said IPPAN had already submitted a detailed report outlining the policy and administrative measures needed to rebuild flood-damaged hydropower projects.
IPPAN has demanded that project licences be extended to 50 years in accordance with the Electricity Act, 1992.
The floods have also forced projects that were nearing the final stages of construction or preparing to begin commercial operations to undergo reconstruction.
IPPAN maintains that private developers are ready to begin rebuilding without direct financial assistance from the government, provided legal, administrative and technical obstacles are removed.
Energy producers say the government needs to address the reconstruction framework for hydropower projects, final settlement of insurance claims, licence duration, construction of safer infrastructure and long-term investment arrangements.
Energy producers have also expressed concern that the disaster has dealt a serious blow to confidence across the private energy sector, particularly after the Langtang Hydropower Project, which was on the verge of starting commercial production, was hit by the devastating Bhote Koshi floods.
They said developers who had been preparing to generate electricity after bringing their projects to the final stages of construction have suddenly been forced back to the initial stages of reconstruction, leaving the sector deeply discouraged.
Private property worth RS 79.17 billion damaged
According to the Post Disaster Needs Assessment (PDNA) released by the National Planning Commission and a report prepared by a government technical team, the floods caused damage worth around RS 79.17 billion to private property alone.
The government estimates that more than RS 723.31 billion will be required to rebuild and restore the overall economy and physical infrastructure.
The floods caused extensive damage to more than 7,500 private homes, dozens of bridges, around 55 kilometres of roads and electricity infrastructure in Rasuwa, Nuwakot, Dhading, Gorkha and Chitwan, among other districts.