February 10, 2017 21:25 pm
KATHMANDU, Feb 11: NMB Bank Ltd says it has successfully executed the financial closure of Upper Solu Khola Hydropower Project which has an installed capacity of 18 MW.
June 20, 2016 09:20 am
KATHMANDU, June 20: The parliament’s Public Accounts Committee on April 22 had said it would end a controversy over procurement for Solu Corridor Transmission Line within a week but since then it has not held a single formal meeting on the issue.
April 25, 2016 00:00 am
KATHMANDU, April 22: The Public Accounts Committee (PAC) of the parliament on Friday launched investigation into a decision to award the contract to build Solu Corridor Transmission Line Project, directing all concerned to stop project's work until further notice.