Nepal completes load flow test

February 23, 2020 11:14 am

RASUWA, Feb 23: The work of testing load flow from the Nepali side has been completed. The test is a necessary step toward the import and export of electricity from China after the construction of the inter-country transmission line, according to Nepal Electricity Authority.

RASUWA, Jan 23: Nepal and China are conducting load flow test within third week of February as part of preparation to build the first cross-border transmission line.

KATHMANDU, Jan 22: A tower of 132 kV Marsyangdi-Syuchatar transmission line, is at high risk of getting swept away by a landslide due to the construction of a hotel nearby.

KATHMANDU, Jan 21: Nepal Electricity Authority (NEA) has taken initiative to resolve differences with locals of Gorkha who have been obstructing construction of 220 kV double-circuit Marsyangdi Corridor Electricity Transmission Line.

KATHMANDU, Oct 19: An agreement to complete the construction of Duhabi-Katari 33 KV transmission line within 45 days has been signed.

TIKAPUR, Oct 12: The under-construction 6-lane road in Tikapur has been affected by the Nepal Electricity Authority’s (NEA) 33 KV transmission line. The construction has been affected as the authority has delayed shifting the poles of the transmission line.

KATHMANDU, Sept 23:With elimination of load-shedding, Nepal Electricity Authority (NEA) has now shifted its focus on construction of transmission line and substations across the country for smooth power supply.

KATHMANDU, Aug 8: The works relating to the construction of two mega projects having strategic importance have begun.

KATHMANDU, Aug 6: The third section of the transmission line of strategic importance, Kabeli Corridor Transmission Line, has finally come into operation by overcoming decades-long disputes.

RASUWA, Aug 3: Additional 30 megawatt of Upper Trishuli 3A has been connected to the national transmission line. According to Fanindra Joshi, chief of the project, total 60 megawatt of the project has been connected to the system including the 30 megawatt added Friday morning.

Your daily dose of missed important news of the day.

PANCHTHAR, March 19: Even after the passing of the fourth extended deadline, the Kabeli Corridor Transmission Line which was to connect the electricity produced in the eastern hilly districts to the central grid still awaits completion. The latest deadline was February 7 this year.

KATHMANDU, Jan 13: A task force has been formed to solve the problems facing the Koshi corridor transmission line project in Dharan area.

NUWAKOT, Oct 25: Stringing work on Upper Trishuli-Matatirtha (Kathmandu) of 220 KVA transmission line started from Wednesday.

KATHMANDU, Sept 23: The government on Friday declared a 300-kilometer-long transmission line implemented under the US government grant of US$ 500 million as a national pride project.