KATHMANDU, April 15: The much-anticipated breakthrough of the Nagdhunga Tunnel was achieved on Monday with the successful completion of the excavation of the 2,688-meter-long main tunnel.

KATHMANDU, March 12: The construction of the Nagdhunga-Sisne Khola Tunnel started from three sections on December 23. The work is being carried out 24 hours a day.

KATHMANDU, Feb 29: The construction of the Nagdhunga-Sisne Khola tunnel from the Dhading side is expected to begin soon. The construction work was halted for the past two months.