SURKHET, April 17: The drilling of a tunnel with the use of a Tunnel Boring Machine (TBM) has been completed in Nepal for the first time. With the help of the TBM, the 12.2 kilometer tunnel for the Bheri-Babai Diversion Multipurpose Project, a national pride project, has been completed about a year ahead of schedule.

Replicate the model of Bheri-Babai

April 8, 2019 01:25 am

Here is something for which the government of K P Sharma Oli can take credit, though his administration alone may not have contributed to it. The construction of 12.2-kilometer long tunnel of Bheri-Babai Diversion Multipurpose Project, a major component of Nepal’s national pride project, is almost complete and this is happening a year before the deadline and without raising additional budget costs.

KATHMANDU, April 7: At a time when almost all major development projects are plagued by persistent delays, the story of Bheri-Babai Diversion Multipurpose Project is going to be somewhat different.