Postal Highway: Deadline extended five times but construction still incomplete

Published On: April 6, 2023 01:00 PM NPT By: Republica  | @RepublicaNepal


MAHENDRANAGAR, April 6: The construction of the Hulaki Road aka the Postal Highway here has not been completed although the deadline of the project has been extended five times.

The construction of 62 kilometers of the highway from Dokebazaar to Bedkot of Kanchanpur district should have been over in 30 months had the construction works moved ahead smoothly. The contract for this segment of the road project was signed in March 2017.

Twenty-six kilometers of the section of the highway in Kanchanpur district remain to be blacktopped. Engineer at the Hulaki Highway Project Office, Deepak Sunar accepted that there has been delay in the construction of the highway.

"The delay was due to the COVID-19 pandemic and taking approval from the national park office. The construction is not complete yet even after extending the deadline five times," he said.

The construction of 62 kilometers of the Hulaki Road was begun after awarding the contract in three phases. The first phase included a 20 kilometers section from Dokebazaar to Belauri. Ninety percent works have been completed on this section. However, the construction remains incomplete in the remaining two sections.

Sharma-Rajendra JV had been awarded the contract for the construction of the road in the first package at a cost of Rs 364.7 million.

The estimated cost for the construction of the 20 kilometers road from Belauri to Beldandi under the second package is Rs 414.1 million. Only nine kilometers of the road in this section has been blacktopped so far, Sunar said. The construction has halted in the Chui area on this section due to the obstruction from the Indian side. The Indian security bodies have obstructed the blacktopping of the road in this location claiming the road passes through the Indian territory.

The Babahansa Siddhisai JV, the construction company responsible for carrying out the construction under the second package, has hardly completed 50 percent of the work.

Similarly, only eight and half kilometers of the 22-kilometer section of the highway from Beldandi to Daiji has been blacktopped under the third package in a span of six years.

"The deadline for completing the works under the second and third package has been extended till mid-July this year. Only 36 kilometers of the highway has been asphalted in six years since the deadline was last extended," Sunar lamented.

The local municipalities through which the road passes have been exerting pressure from time to time for the timely completion of the construction works.


Leave A Comment