Hydro-mechanical work delay hits progress of Upper Tamakoshi

Published On: November 15, 2018 07:57 AM NPT


Mega project is mulling over awarding Texmaco’s remaining work to another contractor

DOLAKHA, Nov 15: Officials of Upper Tamakhoshi Hydropower Project are worried that delay in hydro mechanical works of the project by an Indian contractor will prevent it from meeting the construction deadline.

Frustrated with the work pace of Indian firm Texmaco, the project authority is mulling over assigning some of the hydro mechanical works to another contractor to ensure that the project is completed in time.

Project officials say that they expect the hydropower project of 456-megawatt capacity to start test generation by mid-July next year. The much-awaited project is expected to be a game changer for the country as the supply of the energy from Upper Tamakoshi is expected to end the reliance on Indian imports. 

Nepal is currently importing over 350 MW of electricity during peak hours from India to meet the shortfall of energy. 

As the delay by the Indian firm risks pushing the deadline further, the project officials are now considering to hand over remaining hydro mechanical works to another contractor of the project.

The national pride project had awarded civil, hydro mechanical, electro mechanical and transmission line works to four separate contractors. Of the four contractors, the work progress of Texmaco has been very slow, according to the project officials.

Under hydro mechanical works, the Indian contractor should, among others, lay down pipes in the tunnel and the dam site. According to project officials, Texmaco has to install 197 big pipes in the tunnel something which is overdue.

Similarly, it is required to install 124 pipes of 2.5 meter diameter and 73 pipes of 5 meter diameter from the dam site to the powerhouse.

However, the contractor has been dawdling, citing various reasons. For example, it has been saying that it is facing difficulty in transport pipes due to delay in widening of Lamo Sanghu-Jiri road. It also maintains that some pipes are still being manufacturing in Kolkata, India.

The project is preparing to hand over the remaining hydro mechanical works to Andritz Hydro -- the electro mechanical contractor of the project. The company has already been assigned to carry out re-inspection of the pipes installed by Texmaco.

Bigyan Prasad Shrestha, chief of the project, said that they were considering assigning remaining works to another contractor to complete the project in time. “Almost all works are reaching the final stage. You can rest assured that the test transmission of electricity from this project will begin from mid-July next year and commercial generation of the electricity from mid-November next year,” he said.

The cost of the project, which is being built by mobilizing domestic resources, is projected to reach Rs 49.29 billion, up from the initial estimate of Rs 35 billion. However, after adjusting interest payment, the cost will go up to Rs 70 billion, up from the initial estimate of Rs 47 billion. 

The project has been paying interest up to 12 percent per annum for loans taken to build the plant.


Leave A Comment