Flooding in Relekhola dam halts power production

The project with six megawatts capacity stopped generating electricity completely after the flood inflicted damage to the dam located at the base of Relekholā. 
alt=
By REPUBLICA

MYAGDI, Oct 2: The Relekhola Hydropower Project in Annapurna Rural Municipality-4, Narchyang, Myagdi, has been shut down after floodwaters entered into its dam. 



The project with six megawatts capacity stopped generating electricity completely after the flood inflicted damage to the dam located at the base of Relekholā. 


Related story

Home Ministry warns of releasing excess water from Kulekhani Da...


According to project chief Darshan Kafle, the power generation has completely stopped due to the damage caused to the dam following rain and floods on September 24-27. 


Since the dam is located in a geographically remote and isolated area, the access roads are blocked by landslides, making it difficult to divert the water and operate the project. 


The project, completed last year, connected its electricity to the central grid through a 220 kV Dana substation. 


Floods and landslides from the Kaligandaki River have washed away transmission line towers and broken wires. 


 

Related Stories
OPINION

Ensuring dam safety

sunkoshi.jpg
WORLD

China starts construction of Tibet mega-dam

WPPAN3KYMG9aX83ZlLr9GQKZfCz5NhSsgDecoWaS.jpg
ECONOMY

Construction of Upper Myagdi-I Hydropower Project’...

hydropowerenergy_20220812141412.jpg
SOCIETY

Fewa Siltation Dam: Construction company to repair...

1628935130_siltetiondamm2-1200x560_20210814175046.jpg
ECONOMY

Technical assessment of Upper Tamakoshi dam site b...

UpperTamakoshiDamPhoto2_20200316094025.jpg