BETRAWATI, Jan. 3: Power generation from Trishuli Hydropower Centre in Nuwakot district has disrupted following a fire in the powerhouse occurred last evening.
As a result, 53 MW of electricity (including 21 MW from Trishuli and 14 MW from Devighat Hydropower) and has been disconnected from the national transmission line.
Chief of Trishuli Hydropower Tara Dutta Bhatta said that a generator of 6.6 KV of Breaker No. 6 was completely destroyed in the fire that happened following the excessive heat generation in the electricity transmitter.
Bhatta added that around 10 million rupees would incur to repair the damaged equipment while around a week is expected to take to resume the power transmission from the Centre.
Earlier, fires had occurred on July 10 and November 24, 2018, in the powerhouse. RSS
POKHARA, Sept 5: A house caught fire when residents tried to set fire to a hornet nest last night at... Read More...
POKHARA, September 5: A house caught fire when residents tried to set fire to a hornet nest last night at... Read More...
KATHMANDU, Dec 4: Jeffrey D Sachs, a world-renowned professor of economics, has said that hydropower is one sector that can help... Read More...
Leave A Comment