684 kms of water supply pipeline installed under Melamchi project

KATHMANDU, April 20: Six hundred eighty-four kilometers water supply pipeline has been installed so far under the Me...
By

KATHMANDU, April 20: Six hundred eighty-four kilometers water supply pipeline has been installed so far under the Melamchi Water Supply Project. 


The project has estimated to install a total 720 kilometers of pipeline within 45 days but 684 kilometres has been completed in the first phase so far. 


Related story

55-Kms of pipe-laying works remains under Melamchi water supply...


The Kathmandu Upatyaka Khanepani Limited Project Implementation Directorate spokesperson Lila Prasad Dhakal said 69 kms pipes have been installed out of 77 kms under the main supply system. 


Dhakal said the objective is to complete the task of laying down water supply pipelines by this July 16 under the first phase. Blacktopping of the sections of the roads which had been dug for installing the pipelines is also ongoing. 


The Directorate itself is undertaking the blacktopping works on roads which are less than eight metres wide while the Road Division Office is blacktopping the roads more than eight metres wide, spokesman of the Department of Roads, Mukti Gautam, said. 


He said valve chambers are being constructed on the main crossroads. 

He said zebra crossings would be painted on these spots after the completion of all constructions by July 16 this year. RSS

Related Stories
ECONOMY

Test supply of Melamchi water conducted on 532 kms...

1 min read
ECONOMY

Only 12.2 km remain for laying fuel pipeline of Mo...

1 min read
SOCIETY

Locals threaten to halt Melamchi water supply

1 min read
ECONOMY

Authorities decide not to immediately shut down Me...

1 min read
ECONOMY

Prime Minister Dahal's landlord stalled the Melamc...

1 min read