Kaligandaki transmission Project sees 45 per cent completion

Published On: May 26, 2019 11:20 AM NPT By: RSS


NAWALPARASI, May 26: The construction of the Sub-station under the Kaligandaki Transmission Corridor project in Surya Basti of Sunawal municipality-13 has seen around 45 per completion.

The construction of the Badera Suryabasti (new Butwal 220/132 KV Substation) under the Kalikandaki Transmission line will be completed in around four months.

In the 220/132/33/11 KV Substation will see the installation of three transformers in the first and second phase, according to the project Chief Chandra Kumar Ghosh. The Sub-station will help manage the demand and supply of power.

Construction is also underway to link the Dana sub-station in Myagdi to the Station in Kusma and west Nawalparasi. India's Shree Tata Projects Limited is the contractor company for the construction work. Under the new Butwal section, the 88-km long transmission line starts from Kusma of Parbat to Baglung, Syangja, Palpa, Rupandehi and ends at Badera of west Nawalparasi.

Another 20 kms will be constructed from Butwal to Bardaghat in west Nawalparasi.