Renovation of Bhotekoshi Hydro to take another year and a half

Published On: May 12, 2018 09:10 AM NPT By: Dhruba Dangal


SINDHUPALCHOWK, May 11: The 45 megawatt Bhotekoshi Hydropower Project, whose construction was hindered time and again because of natural disasters that hit the project one after another, will possibly take one and half more years to come into operation. 

The renovation of the project, considered to be the largest constructed by the private sector, is underway so that the plant can come into operation by the end of 2019.

The project devastated by the flood that hit the site on July 5, 2016 as a result of the bursting of a lake in Tibet is being renovated since the past six months according to Bikram Ratna Sthapit, chief executive officer of the Bhotekoshi Power Company Pvt Ltd. “The project is being constructed at a very fast pace. However, it will take one and half years for the project to complete,” said Sthapit. 

He added that Sino-hydro is working on the reconstruction of the project after securing a tender of Rs 5 billion. However, as they have to work on the development of other infrastructures along with the said contract as well, the reconstruction bill for the project has swelled to Rs 7 billion, added Sthapit. 

The flood greatly affected the dam site and the power house, causing the reconstruction of the project to equal initial construction bill. 

Before this, the construction work was affected by the 2015 earthquakes followed by the floods and landslides last year, halting construction work and affecting newly constructed infrastructure. 

Sthapit told Republica, “Although the 3.3 kilometers of tunnel was not affected by the floods, the calamities caused damage in electromechanical infrastructures over civil infrastructures. So the reconstruction work will be lengthy.” He added, “The construction cost was itself high. But as we also have to dismantle the damaged parts, the construction cost will increase.”

 When 80 percent renovation work after the earthquake damages were completed with an investment of US$ 25 million, the project was again hit by the floods causing even more disturbance than what the earthquake had caused.