CHAUTARA, Feb 5: Thirty-five per cent earthquake-affected people in Sindhupalchok district have not yet reconstructed their houses. Sindhupalchok is one of the worst affected districts from the April 25, 2015 devastating earthquake.
The quake survivors have not been able to rebuild as they spent the first tranche of the house construction grants for domestic purposes and also because of the shortage of money and skilled construction workers, coupled with sky-rocketing cost of construction materials.
When will it end?
There are 78,537 registered earthquake survivor beneficiaries in the district. Additional 5,126 quake survivor families, who were left out from the first list of beneficiaries, were registered later.
Chief of the Urban Development and Building Construction Division Office, Tanka Gautam said so far only 65 per cent of those registered beneficiaries have started constructing their houses in the district.
Forty thousand three hundred and fifty families have been recommended for the second installment while 5,486 families recommended for releasing third installment of the government grants, Gautam said.
Meanwhile, 63 earthquake-affected families who were displaced after their locale developed cracks and gaps following the earthquake have been settled in a safe place by purchasing housing plots for them. Among these families, 18 are from Bahrabise Municipality and 43 are from Indrawati rural municipality. So far 521 families in the district have been identified as living in at risky areas in the district.(RSS)