Published On: July 28, 2016 12:46 PM NPT By: Republica | @RepublicaNepal
MYAGDI, July 28: Three micro-hydroelectricity projects have stopped production as they were damaged by the flood and landslides triggered by continuous rains.
The 35-Kilowatt Second Darkhola Hydroelectricity project and the 60- Kilowatt First Darkhola Hydroelectricity project have stopped power production due to the damage caused by a landslide at local Lulang.
A huge landslip has washed away some 150 metres of the water channel of the project, besides putting the powerhouse at high risk, Keshar Bahadur Purja, a local, said.
The landslide has washed away two cowsheds and put a few houses at risk.
Similarly, the 30-Kilowatt Dajungkhola Micro Hydroelectricity Project has halted production for the last three days after the flood swept away the project's water canal. RSS
PARBAT, Aug 10: After the flood triggered by the breach of Turture Lake damaged roadway here Monday, the vehicular movement... Read More...
PHALEBAS ( Parbat), Dec 3: Many of micro hydro-power projects based in rural parts of Parabat, eight are not in... Read More...
DANG, July 29: Small and marginal farmers in Banke have suffered due to crop loss caused by recent floods in... Read More...