Locals padlock Chameliya project office

alt=
By No Author
MAHENDRANAGAR, July 13: Construction work at Chameliya Hydropower Project remained stalled for the second consecutive day on Monday after locals padlocked the project´s office after submitting a 22-point demand to the project officials on Sunday.



The demands include employment opportunities for locals, increasing compensation amount for acquisitioned land, and construction of roads and schools among other development activities in the area. Locals have accused the project officials of not paying heed to their demands.



Rabindra Bhatta, an accountant of the project, said that the locals also vandalized the project office on Sunday. "There is no environment to continue work in the office," said Bhatta.



Security personnel had fired five bullets in the air to disperse the mob and bring the situation under control.



Related story

Testing of 40 MW Upper Chameliya Hydroelectric Project commence...

Related Stories
ECONOMY

Chameliya finally starts generating electricity

chameliya.jpg
ECONOMY

28.304 MW Madhya Chameliya Hydropower Project fina...

1670375548_mahakali-1200x560_20221207100231.jpg
ECONOMY

Foundation stone laid for 40-MW Upper Chameliya pr...

Upper-Chameliya1_20201017201427.png
SOCIETY

Chameliya hydel project to generate power commerci...

Chameliya hydel project to generate power commercially from Saturday
ECONOMY

Chameliya project completed after a decade

Chameliya%20power%20house.jpg